EnronWind button title ENRON
Section
Press Releases 

Case Studies 

Community 

Just for Kids /Teachers 

Photo Library 

Wind Energy Links 

Press Release Archives 

Contacts 

 

HOME page
 
Case Studies

    Storm Lake, Iowa
    193 MW Wind Generation Facility
    Project Information


Power Purchasers

    MidAmerican Energy Company - Headquartered in Des Moines, Iowa. In March 1997 Enron Wind entered into a long-term agreement with MidAmerican to provide 113 MW of clean, wind generated capacity to the MidAmerican grid.

    IES Utilities, a subsidiary of Alliant Energy - Headquartered in Cedar Rapids, Iowa. In July 1997, Enron Wind also entered into an agreement with IES Utilities to provide IES with 80 MW of wind generated capacity.

Project Developer/Operator

    Enron Wind developed, constructed, and operates the Storm Lake project.

    A pioneer and leader in the wind industry since 1980, Enron Wind is a vertically integrated company. The company has developed and constructed over 4,500 wind turbines, comprising more than 1,600 MW. Enron Wind in North America and Europe, develops and manufactures state-of-the-art wind turbine technology ranging from 600 kW to 1.5 MW.

Project Location

    Northwestern Iowa, in Buena Vista and Cherokee counties near the community of Alta.

Power Purchase Agreement

    Signed: March 1997/July 1997
    Term: 20 Years
    Power Capacity: 193 MW (the single largest wind power project in the world today)
    Annual Generation: approximately 650,000 megawatt hours per year
    # Wind turbines: 257

Technology

    Manufacturer: Enron Wind
    Wind Turbine Type: Zond Z-750 kW Series

    Enron Wind's Z-750 kW Series wind turbines utilize a variable speed, constant frequency configuration providing selectable power factor, improving power quality and increasing the aerodynamic efficiency of the turbines while reducing mechanical loads.
    At the time of the project, the Z-750 was the largest wind turbine manufactured in the United States. Now in the year 2000, Enron Wind's 1.5 MW wind turbine is also manufactured in the United States.
    The project’s Z-750 kW Series wind turbines hold certification by Germanischer Lloyd to IEC Class II for a 30 year fatigue life. IEC Class II requires a wind turbine to withstand hurricane loads of up to 131.1 mph (59.5 meters per second) as a once in a 50 year occurrence, and 99.8 mph (44.6 meters per second) as a yearly occurrence.

    Rated Output: 750 kW

    Foundation:
    Each wind turbine foundation consists of four individually drilled caissons - 5 ft. in diameter and 35 ft. deep.
    Footprint: 40' x 40' - spaced 1 - 2,000 feet apart
    Concrete: 200 tons per foundation (51,400 tons to complete all 257 foundations, or 3060 full concrete truckloads - enough to make a 3' x 3" sidewalk approximately 157 miles long.)
    Steel Reinforcement: 5 tons per foundation (1,285 tons to complete all 257 foundations)

    Tower: Lattice Configuration
    Height: 208 feet (63 meters) - 12 ft. at base tapering to 8 feet at the top.
    Weight: 57 tons (114,000 lbs.)

    Blades:
    Length: 79 ft. (24 meters)
    Rotor Diameter: 164 ft. ft. (50 meters) – approximately the size of the wingspan of a MD-11 jumbo jet
    Revolutions per minute: 18-34 (one revolution every 2-3 seconds)

    Swept Area: 21,124 sq. feet per turbine or approximately 5.5 million sq. feet for the two projects combined. To capture the same area of wind, it would take the equivalent of a sailing ship the size of the SuperBowl stadium with a mast over half a mile high.

Construction

    Groundbreaking: October 1998
    Completion: June 1999

    Schedule:
    September 1998 - Grading of roads, turbine pads and foundations began. Collection system lines were placed underground in the farm fields and overhead on poles near roads. Substation was constructed. Turbines and towers began arriving at the site and erection activities began.

    January 1999 - Substation was completed and erected turbines began to be placed on line - turbine erection activities continued.

    June 1999 - Project completed

Environmental Benefits:

    The installation will provide enough electricity to serve approximately 72,000 average Midwestern households, or 192,000 people. If coal were burned to generate the same amount of electricity, over 301,000 tons per year would be required.*

Annual Offsets:

    The 257 Enron WInd 750 kW Series wind turbines can be expected to offset 1 billion pounds (502,000 tons) of carbon dioxide, the leading greenhouse gas associated with global warming, based on U.S. average fuel mix. Other emissions offsets include: 5.2 million pounds (2,600 tons) of sulfur dioxide - the major cause of acid rain, pollution of waterways, and air-born particulate pollution; and 3.4 million pounds (1,700 tons) of nitrous oxide.

Jobs Created:

    Construction Jobs: 150
    Ongoing O&M Jobs: 20-30

 

 

Back to top

Back to Case Studies

 

* Information provided by the American Wind Energy Association
©1999 Enron Wind